Tuesday, March 20, 2007

Progress Update

Lots of things were happening yesterday.
The grid ceiling installation began and will be completed today. Ryan and I set a number of cabinets, including the merchandise cabinets that are mounted to the south wall. Rob began laying tile in both bathrooms. I built the forms to pour a concrete pad for the hot water heater. It has to be on a 24"x24" by 12" high platform per code. The platform cannot be made of wood, so I am going to pour a big concrete block for it.
I took measurements for the floor grate that will go over the grease trap in the back room. I need to visit Neil Dana today and get it fabricated. I also measured for the window counter height seating and will buy Padauk and Maple to start building those.
Ryan modified our sink and set it into the cabinet base yesterday as well. Allied order the wrong type of glass fill station for us, and I need to take it back today.

We met with John from Spectrum Signs yesterday. I have to take our business card artwork and create a horizontal sign in the same theme. This is a rough draft so far:



We are also going to have a 5'x5' lighted sign on the back of the building, and two 10' long temp banners on some tall sign posts out buy the road.

Gotta run...
JD

No comments: